Nutan Bidyut (Bangladesh) Limited

ROAD MAP

  • LOI Awarded on 18th April 2016
  • Project Agreement Signed on 28th August

    NTP to EPC contractor on 21st September

    Project acquired land from BPDB on lease on 18th November

    2017
  • Financial Close on 28th May 2018
  • Project Achieved COD on 9th June 2021
  • Project invested by Actis on 16th June

    2022